With LIV Golf infrastructure works well underway, we would like to provide members with a progress update on the build.
Works underway or completed
- Construction works are virtually complete on “The Watering Hole” (or 12W)
- Construction works are virtually complete on the Club 54 & Chalets build around the 18W green
- Construction works are virtually complete on Barossa hospitality area adjacent 14W, 15W & 16W
- As of 7th April, 17 of 22 camera towers builds were complete or underway, and 10 of 20 superscreen builds were underway
- All 10 corporate hospitality builds are in progress
- Construction works on 5 of 12 viewing decks are underway
- The Flight Deck infrastructure build on the driving range commenced on Tuesday, 9th April
- The Media Centre and broadcast compound builds commenced on 2nd April
- Fan Village infrastructure works on 1st and 2nd West underway
Works coming up
- Viewing decks on the 1st East tee and putting green commence shortly
- The C-Suites infrastructure build on the Pro Shop terrace commences on Wednesday, 10th April
- Media Centre in clubhouse car park
- Watering Hole – view from the Cellar Door
- 14W green (14th LIV)
- Watering Hole – view from the Front Bar
- Birdie Shack adjacent 10E green (1st LIV)
- Barossa hospitality adjacent 14W, 15W & 16W (14th, 15th & 16th LIV)
- Channel 7 Media Call at Watering Hole
- Broadcast compound in clubhouse car park
- Aerial view of 14E (5th LIV)
- Watering Hole – 12W (12th LIV)
- 18W green (18th LIV)