With LIV Golf infrastructure works now underway on the golf course, we would like to provide members with a weekly progress update on the build.
Works underway or completed
- Construction continues around “The Watering Hole” (or 12W), with works currently underway on the Front Bar, Beach Club, Shark Shack and Cellar Door hospitality areas
- Construction commenced on the Club 54 & Chalets build around the 18W green
- Construction commenced on Barossa hospitality area adjacent 14W, 15W & 16W – including TV towers and superscreen scaffolding
- Committee car park closure from 18th March for use as a staging site for construction works – contractors providing access to the area, as required, on busy days for member car parking
- Camera tower builds commenced on 20th March – a total of 22 camera towers will be constructed. As of 22nd March, 4 camera towers are in progress.
- 9 out of the 10 corporate hospitality builds are in progress
- Preparatory survey work for infrastructure builds in coming weeks was completed on 21st March
Works coming up
- Construction work on the Gallery Club, adjacent the 18E green will commence on Monday, 25th March, with the hole reverting to a temporary par 3
- TV tower and LED screen scaffolding works are continuing
- Barossa hospitality build, TV towers & superscreen scaffolding adjacent 14th West
- Birdie Shack hospitality adjacent 10th East
- View from the 12th West green
- Beach Club hospitality on the “Watering Hole”
- Club 54 & Chalets hospitality adjacent 18th West