With LIV Golf infrastructure works now underway on the golf course, we would like to provide members with a weekly progress update on the build.

Works underway or completed

  • On-site works have been centered around “The Watering Hole” (or 12th West), with scaffolding works currently underway on the Front Bar, Beach Club, Shark Shack and Cellar Door hospitality areas
  • Pavement crossing works on the 13th West, including the exposed aggregate pathway across the fairway, the bitumen pathway extending to Classic Court, and the cart path spurs to the 13th tees, are now complete.

Works coming up

  • Scaffolding works will commence shortly on the “Barossa” hospitality area adjacent the 14th West green/15th West tee area
  • TV tower and LED screen scaffolding works will commence from 18th March

View LIV Golf Build Report